FIBRE OVERLAY – RANGATIRA
Client: Telcospec / Vocus
​
Location: Rangatira
​
Service: Replacement of fibre along SH1
​
Date: February - May 2024
​
​
Challenges
Telecospec / Vocus decided to install new fibre optic cables in parallel with their existing ones to replace the damaged ones.
​
Solution
Marais Laying NZ proposed the use of the trenching machine ST2 to install the new subduct alongside the existing fibre optic cables.
​
Result
This project prompted us to introduce a new range of cable installation solutions, ultimately boosting productivity.
Utilizing the laying box eliminates the need for employees to work in the trench, while also ensuring the automatic installation of the conduits.
​
Key facts:
-
7km of trench along SH1
-
1 bridge crossing
Key equipment used:
-
Laying box