FIBRE INSTALLATION - 
OARO SOUTH PROJECT

Client: Downer

​

Location: Oaro

​

Service: Fibre installation

​

Date started: April 2021

Date completed: July 2021

​

​

Scope of work

Changing the damaged and faulty fibre line from Cleverley to Oaro. The work was carried out on the Kiwirail line.

​

Trenched in the Kiwirail accessway.

​

IWI, Vodafone, Downer, Spark archaeologists and Kiwirail were the main stakeholders. Installed both underground and overground fibre cable using various techniques like trenching, thrusting and galv- pipe joinning.

​

​

Challenges

The two main challenges were working near a live railway as well as in a highly archaeologically sensitive area.

​

​

Solutions

Good communications with both the Rail Protection Officer and archaeologist were key to making this project a success.

 

Because of the area’s sensitivity we could not use one of our trenching machines and had to use traditional excavators instead.

​

​

Key fact:
  • 7 km of trenching and thrusting on Kiwirail accessway

  • 1 km of over ground galvanised pipe installation

​

Key equipment used:
  • 8 ton excavator

  • Thruster

MaraisKP-14.jpg

SOME OF OUR CLIENTS

Marais Laying New Zealand specialises in trenching and industrial cable laying, from large scale renewable projects and oil and gas pipelines, to telecommunications and power infrastructure.

​

​

© 2024 by Marais Laying New Zealand | All Rights Reserved

​

Terms of Use

  • LinkedIn
  • Facebook
bottom of page