FIBRE INSTALLATION -
OARO SOUTH PROJECT
Client: Downer
​
Location: Oaro
​
Service: Fibre installation
​
Date started: April 2021
Date completed: July 2021
​
​
Scope of work
Changing the damaged and faulty fibre line from Cleverley to Oaro. The work was carried out on the Kiwirail line.
​
Trenched in the Kiwirail accessway.
​
IWI, Vodafone, Downer, Spark archaeologists and Kiwirail were the main stakeholders. Installed both underground and overground fibre cable using various techniques like trenching, thrusting and galv- pipe joinning.
​
​
Challenges
The two main challenges were working near a live railway as well as in a highly archaeologically sensitive area.
​
​
Solutions
Good communications with both the Rail Protection Officer and archaeologist were key to making this project a success.
Because of the area’s sensitivity we could not use one of our trenching machines and had to use traditional excavators instead.
​
​
Key fact:
-
7 km of trenching and thrusting on Kiwirail accessway
-
1 km of over ground galvanised pipe installation
​
Key equipment used:
-
8 ton excavator
-
Thruster